FHS Track Reconstruction Timeline
(Due to our track reconstruction project, the FHS Track will be CLOSED from June-August, 2024)
(All dates below are estimates and subject to change due to weather, supply chain issues, etc.)
Fenton High School Track Reconstruction
Start Date | Track Reconstruction Activity | Bid Work | Bid Awarded to: |
---|---|---|---|
6/11/24 | Demolition of existing track | Exterior Concrete | Albanelli Cement Contractors |
6/17/24 | Trench drain | Asphalt paving | Asphalt Specialists |
6/24/24 | Pave new track | Track Surfacing | Star Trac Enterprises |
7/1/24 | Track surfacing | Fencing | Motor City Fence |
8/5/24 | Track markings & lines | ||
8/10/24 | Track Project Completion |