FHS Track Reconstruction Timeline

(Due to our track reconstruction project, the FHS Track will be CLOSED from June-August, 2024)

(All dates below are estimates and subject to change due to weather, supply chain issues, etc.)

A graphic depicting the Fenton Area Public Schools bond project design schedule for the High School track reconstruction. The schedule spans from January 2024 to December 2025 and includes phases like schematic design, bid development, and construction. The project is funded by sinking fund dollars and was projected to be completed by September 2024.  It appears to be completed ahead of schedule.

Fenton High School Track Reconstruction

Start Date

Track Reconstruction Activity

Bid Work

Bid Awarded to:

6/11/24

Demolition of existing track

Exterior Concrete

Albanelli Cement Contractors

6/17/24

Trench drain

Asphalt paving

Asphalt Specialists

6/24/24

Pave new track

Track Surfacing

Star Trac Enterprises

7/1/24

Track surfacing

Fencing

Motor City Fence

8/5/24

Track markings & lines

8/10/24

Track Project Completion