AGS Middle School Construction Timeline

(All dates below are estimates and subject to change due to weather, supply chain issues, etc.)

A graphic showing the Fenton Area Public Schools bond project design schedule for the AGS building.  The schedule outlines the phases for constructing a new main office addition, spanning from January 2024 to December 2025. It includes construction design, plan review, and construction phases. The projected completion is September 2025.

AGS Main Office Addition

A graphic showing the Fenton Area Public Schools bond project design schedule for the AGS building.  The schedule outlines the phases for constructing a new science lab and special services office, spanning from January 2024 to December 2025. It includes schematic design, construction document development

AGS Science Lab & Special Services Office Project

Youtube logo

Click this link to view a LIVE Video Feed of our AGS Main Office addition.

Start Date

Project

Bid Work

Bid Awarded to:

7/1/24

Sitework & Utilities

TBD

7/18/24

Foundations

8/12/24

Masonry

9/2/24

Steel

9/18/24

Exterior Envelope

9/23/24

Underground MEP

10/14/24

Concrete Slab

10/21/24

Overhead MEP

11/18/24

Interior Framing

1/13/25

Drywall

3/31/25

Exterior Finishes

2/24/25 - 6/6/25

Interior Finishes

Start Date

Project

Bid Work

Bid Awarded to:

TBD

TBD

TBD

TBD